How long does a restaurant fit-out take?

There is no single answer — but there is a predictable sequence, and most delays come from the same few places.

Alessio Giorgetti, director of re:SPACE, turnkey fit-out company in London
· 6 min read
Kitchen counters and dining tables at Mercato Mayfair food market, London

Why there is no standard restaurant fit-out timeline

A restaurant fit-out takes as long as its slowest dependency. For a unit with existing restaurant use, services and an extraction route, that is usually the build. For a listed building needing change of use, it is almost always the consents.

The five stages of a restaurant fit-out

Every project we deliver runs through the same sequence, from 75 sq ft to 26,900 sq ft:

  • Feasibility: survey, brief test and risk register
  • Design: concept through to a frozen technical design
  • Consents: planning, heritage and licensing lodged in parallel
  • Build: strip-out, first fix, joinery, equipment, finishes
  • Handover: commissioning, snagging, training, first service

What extends a fit-out programme

The same four items account for most delays we are asked to recover:

  • Change of use or heritage consent not identified at feasibility
  • No acceptable route for kitchen extraction
  • Incoming power or drainage that needs upgrading
  • Design changes after procurement has started

How to protect your opening date

Freeze the design before ordering long-lead equipment, and run consents alongside the build rather than ahead of it. In Barcelona, Badiani’s activity licence covering both B2B production and B2C retail was secured as a single dual-use application, with both uses applied for simultaneously. That avoided a second process after opening.

Red illuminated signage inside the Badiani gelato laboratory and shop in Eixample, Barcelona
Case study referencedBadiani Eixample →Badiani's first gelato laboratory in Spain.
FAQ

Frequently asked questions

Q1

How long does a restaurant fit-out take in the UK?

It depends on the condition of the unit and the consents it needs. A site with existing restaurant use and services moves quickly; a listed building or change of use takes longer because consents set the pace. We set a programme at feasibility stage, once the site has been surveyed.

Q2

Can a restaurant fit-out be done faster?

Yes, by running workstreams in parallel. Consents can progress alongside technical design, long-lead equipment can be ordered once the design is frozen, and trades can be sequenced so they do not wait on each other. Appointing one turnkey team makes that coordination possible.

Q3

What causes the most delays in a restaurant fit-out?

Unidentified consents, kitchen extraction and inadequate incoming services are the most common. All three can be found in a feasibility survey before the lease is signed. Late design changes are the fourth, which is why we freeze the design before procurement.

Q4

When should I appoint a fit-out contractor?

As early as possible, ideally before signing the lease. A contractor involved at feasibility can identify consents, services and extraction issues while there is still time to plan around them, which is the most effective way to protect the opening date.